The New Precision Craft Dental Lab

Friday, September 29, 2006

Progress as of 9/28... Masonry is complete, window framing completed as well. And, what we have all been waiting for: The Electrician is showing signs of life! What a beautiful sight..
Glass ready and waiting for installation starting today, 9/29. Smoke brown color...nice
 Posted by Picasa

Thursday, September 21, 2006

Managers Visit

First tour of the building for Marco, Linda and Jeff. Everyone wanted to stay...it was tough to get them back to the lab and back to work!! Two weeks until drywall.... Posted by Picasa

Tuesday, September 19, 2006

Moving Along Nicely

Things seem to be moving along rather nicely as of late. Masonry is now being done, the interior framing is complete, as are sprinklers and ductwork. Looking to have the building lockable and buttoned up at the end of next week. Electrical is falling behind, by about a week, so that is holding up our drywall...which is holding up the painting...which is holding up the benches....which is holding up the equipment.................

Well, another day, more progress. Currently, the interior framing is done, sprinklers and duct work are all moving along, and the electrician, oh the electrician.... We are a week behind in the electrical, so once that is taken care of we can hang the drywall and really get moving. Looks like the building will be buttoned up with windows and doors at the end of next week. Below are a few shots of whats currently taking place. The masonry exterior is going in and should be set by Friday, and then the rest of the wall can be placed. Richard surveying the Partial Frame department as it currently stands.
A view of our Crown & Bridge and Ceramics department with nice large cutouts for some spectacular glass. This really should eliminate any feeling of a maze that you get from being fully enclosed.
 Posted by Picasa

Wednesday, September 13, 2006

Walls are coming along very nicely...we are looking to have the drywall up at the end of next week. A view looking down the hallway to our new conference center...

Construction crew breaking in the new Cafeteria...they beat us to it!!
 Posted by Picasa

Thursday, September 07, 2006

Interior shots. Conference room from what will be the entrance door. Mark Gilchrist surveying the sprinkler work to date. And more walls going up!
 Posted by Picasa

Floor is poured, Walls are going up, interior is being laid out, just too much to talk about!!!!! A view of our conference room from outside.
Installing the exterior wall.
Wall progress in 2 Days! Makes me wonder how long the rest will take.
 Posted by Picasa

Walls are now going up! Another post when the floor is poured! Posted by Picasa


The Roof is up and we are getting into plumbing. Note Richard in the top photo, surveying the work to date. Bottom photo gives a view across the width of the lab. Posted by Picasa


The first photos of our shell going up. 14,222 square feet from 3,140...Yahoo! Below is the front Entrance view...if you can visualize it.
 Posted by Picasa

And revision 23 is the Lucky one!!

Well, its been a while, a loooong while. After many redrafts and revisions, planning sessions and previews, we have the following to report:

1) A final floor plan has been reached.
2) Construction is Underway.
3) Completion is slated for October 2006.

See the updated photos in comparison to below!!

Ryan